Akamas Roadworks Retendered With Stricter Environmental Safeguards

Header Image

A new tender for Phase A roadworks in the Akamas National Forest Park includes tighter environmental controls, continuous monitoring and measures to correct problems identified in the original project.

Three years after Phase A roadworks in the Akamas National Forest Park were suspended over shortcomings in planning, implementation and oversight, the Department of Forests has launched a new tender based on revised construction plans approved by the competent authorities.

The contract, published last Friday, is valued at €5.63 million and is expected to run for 13 months, with works scheduled to begin in early 2027 and conclude in February 2028.

Contractor obligations

Under revised provisions introduced in May 2025, the contractor will be required to implement all measures contained in environmental studies, approvals and conditions issued by the Department of Environment.

The tender incorporates a range of documents, including ecological assessments, environmental approvals, supplementary conditions, compliance reports and requirements arising from the revised road network plans.

Continuous environmental monitoring

The contractor will be subject to ongoing supervision by an environmental inspector appointed by the Environmental Authority.

The inspector will monitor compliance with environmental legislation throughout the project, while the contractor will be obliged to cooperate fully and facilitate inspections.

Agriculture Minister Christos Senekis recently acknowledged weaknesses in previous monitoring mechanisms, including the absence of a clear protocol for recording and reporting deviations.

Correcting past mistakes

The contractor will also be required to implement measures agreed during a July 2026 meeting on the revised plans.

These include:

  • Reducing walls built in the Toxeutra sandstone formations to 20cm.
  • Mechanically removing specific hazardous rocks.
  • Removing water supply hoses and cabling from the park and restoring affected areas.
  • Developing alternative water-supply arrangements for firefighting needs.
  • Limiting excavation in rocky ground to between 15cm and 25cm.
  • Reducing kerb height to 20cm.
  • Restoring affected habitats under a plan already approved by the Department of Forests.

Construction restrictions

The new tender includes mandatory environmental conditions.

Among them:

  • No spoil or excavated material may be dumped on undisturbed land.
  • Work near bird nesting sites may only proceed following consultation between the Department of Forests and the Game and Fauna Service.
  • Coastal roadworks are prohibited during the sea turtle breeding season, from May to October.
  • Dumping of waste or construction materials, as well as vehicle access and parking, is prohibited within the riverbeds of the Aspros and Avgas rivers.
  • Embankments must be covered with topsoil.
  • Metal safety barriers must meet specified standards and be clad in wood.